DOI · DOI-0100 · record R2658
Predicting post-fire tree mortality
Department of the Interior · USGS
Overview
- Development stage
- DeployedSource: c) Deployed – The use case is being actively authorized or utilized to support the functions or mission of an agency.
- High-impact designation
- Not high-impactSource: c) Not high-impact
- Impact justification
- Not reported
- Start date
- 2021-10-01 (day precision)Source: 10/1/2021
- Withheld from public reporting
- NoSource: a) No
Mission
- Topic area
- Science
- Operational functions
- Forecasting and prediction Derived by keyword rules; see methodology
Problem the AI is intended to solve
We used random forests to select predictor variables for models of individual tree mortality following fire.
Expected benefits
These science products strengthen wildland fire and timber management practices.
System outputs
Predictive models of postfire tree survivorship.
Technology
- AI classification
- Classical / predictive MLSource: Classical/Predictive Machine Learning: Models trained on data to make predictions or classifications based on identified patterns or relatio…
- System name(s)
- Not reported
- Custom-developed code
- No
- Public source code
- Not reported
Sourcing
- How it was built
- Developed in-houseSource: b) Developed in-house
- Vendor (as reported)
- Not reported
- Vendors (standardized)
- None on the standard list
A vendor is the supplier named by the agency. It does not identify the underlying model or AI technology.
Data and privacy
- Involves PII
- No
- Privacy Impact Assessment
- Not reported
- Authorization to Operate
- No
- Demographic features
- k) None of the above
- Training and evaluation data
- A database of fire effects to describe the determinants of fire-induced tree mortality.
- Federal Data Catalog
- research.fs.usda.gov ↗
Governance
0 of 8 minimum-practice questions answered. A blank answer means the agency reported nothing; it does not mean the practice is absent.
Pre-deployment testingNo answer reported
AI impact assessmentNo answer reported
Independent reviewNo answer reported
Ongoing monitoringNo answer reported
Operator trainingNo answer reported
Fail-safeNo answer reported
Appeal processNo answer reported
User and public consultationNo answer reported
Potential impacts and how they were identified
Not reported